The Kebao false floor installation is to be done with the company recommended procedure through authorized dealer and installation-contractor. The floor should be hard, level & free form dust / moisture. Two coat of epoxy paint on the existing floor is recommended. Do water level marking & pedestal marking at site prior to installation to avoid overlapping of the services. Complete the cable tray, piping, insulation, and control panel MS stands activity before installing the access floor then lay the complete kebao system including the tile, pedestal & stringer at one starch and place the cut pieces of the tile, fix the pedestal using anchor fastener or epoxy adhesive. Do the final leveling of the false floor jamming the total system from all sides. Remove the center full tiles for placing the cables & other services using panel lifter. Tiles can be cut at site for wire opening & grommet fixing.